Lavally Transportation

Location

  • Sellersburg, IN

Services Provided

  • Asphalt Paving
  • Striping

Duration

  • 2 Weeks

Job Summary

Installing a new semi-trailer parking lot behind Clark County Airport, designed to support increased industrial traffic and logistics operations. This project included the installation of 2,500 tons of material to create a durable and organized space for heavy-duty vehicles, enhancing overall efficiency and capacity in the area.

Challenges

With a tight turnaround, we closely monitored plant production while paving on-site to ensure efficiency. The primary challenge was maximizing production at the plant while working toward closing it, requiring careful coordination and precise planning to meet project deadlines without compromising quality.

Gallery